OCTOBER HIGHLIGHTS:

~Installation of second floor deck at chiller building complete~

~Elevator pit installed~

~Ground floor level poured in place concrete complete at north and west walls of parking garage~

~Installation of formwork for interior columns complete~

~Installation of formwork for radius wall on Estero side of building in progress~

~Installation of vertical steel beams for elevator tower complete~

September 2011

August 2011

July 2011

June 2011

May 2011

This Month on the Construction Site - October 2011