NOVEMBER HIGHLIGHTS:
~Ground floor level poured in place concrete complete on radius wall~
~Remaining poured in place concrete walls on Estero side of building compete~
~Installation of steel framework for elevator tower in progress~
~Columns in parking structure complete~
~Installation of vertical beam through existing roof and stairwell complete~
~Installation of hollow-core floor panels complete~
~Concrete slab over hollow-core floor panels poured and water-cured~




|
This Month on the Construction Site -
November 2011