AUGUST HIGHLIGHTS:
~Entry doors removed and replaced with drywall and temporary, fire exit only door~
~Bay window on Bay Road side removed and replaced with relocated entry
doors~
~Stairs and ramp to temporary entrance on Bay Road completed and open for
use~
~Parking lot striping on pavers completed & mulch installed; lot is open for use~
~Demolition of exterior stairs and ramp on Estero side completed~
~Installation of test piling completed~
~Road work on Bay Road completed~
~Utility work on School Street side in progress; installation of FPL utility pole for power to the church completed~
~Xerxes underground water storage tank installation completed~


 |
This Month on the Construction Site -
August 2011